The Regional Ring Road (RRR) is one of Hyderabad's biggest infrastructure projects, designed to connect outer towns and reduce traffic inside the city. At about 340 kilometers long, this four-lane road will loop around Hyderabad, linking over 125 villages and major highways. Once completed, it's expected to unlock new development zones and increase land value in nearby areas.
The RRR is being built to reduce congestion on Hyderabad's existing roads, especially the Outer Ring Road (ORR), which is already seeing heavy traffic. The RRR will help connect nearby towns and villages directly to highways, giving better access to industries, schools, hospitals, and jobs.
This massive project is part of the Bharatmala Pariyojana Phase 2, a national plan to improve highways across India.
The RRR is being built in two parts:
Northern Corridor – Under ConstructionThis section stretches about 158 km and includes areas like:
Most of the land here has already been acquired, and work is underway.
Southern Corridor – Still in PlanningThis section is about 182 km and runs through:
The government is still finalizing land deals in this area. Construction may take longer.
RRR will connect key national and state highways. This makes travel faster between towns and helps reduce traffic in Hyderabad. For example, it will cut down the travel time to Rajiv Gandhi International Airport and areas like Gachibowli or HITEC City.
2. Real Estate GrowthRRR is opening up new areas for investment. Localities that were once seen as outskirts are now being considered for IT parks, townships, and commercial hubs.
Some hotspots include:The government plans to build new mini-cities along the RRR. These will have IT hubs, schools, hospitals, and clean residential spaces. Projects like Godrej Regal Pavilion are already exploring such zones for development.
Location | Before RRR (₹/sq. yd) | After RRR (₹/sq. yd) |
Bhongir | ₹4,000–₹6,000 | ₹10,000–₹15,000 |
Chevella | ₹3,000–₹5,000 | ₹9,000–₹12,000 |
Toopran | ₹2,500–₹4,000 | ₹7,000–₹10,000 |
Prices are still rising as construction progresses.
Task | Northern Section | Southern Section |
Land Acquisition | 94% Complete | Ongoing |
Environmental Clearance | Granted | Pending |
Construction Progress | Started | Awaiting tender |
Expected Completion | By 2026 | 2028–2030 (target) |
The RRR isn't just a highway—it's Hyderabad's next big leap in planned urban expansion. It will ease city traffic, improve life in the suburbs, and create new opportunities for growth and investment. Projects like Godrej Regal Pavilion are early signs that the region is set for long-term development.
If you're looking to invest or find a home in a quieter, greener space with future city-level connectivity, keeping an eye on RRR-linked zones might be the smartest move today.